Abstract
We present a heuristic algorithm for scheduling jobs in a machining centre equipped with multiple-pallet automated pallet changers (APCs). The algorithm dynamically adjusts the number of pallets used and the priority of each job to minimise the total weighted tardiness. The algorithm was evaluated based on a study conducted at Växjöfabriken, a metal-casting company located in Växjö, Sweden. Results obtained from this study show more than a 40% reduction in the total weighted tardiness of the overall machining park.
Original language | English (US) |
---|---|
Pages (from-to) | 326-336 |
Number of pages | 11 |
Journal | International Journal of Advanced Operations Management |
Volume | 3 |
Issue number | 3-4 |
DOIs | |
State | Published - 2011 |
Keywords
- APC
- Automated pallet changer
- Machining centre
- Scheduling
- Weighted tardiness
ASJC Scopus subject areas
- Organizational Behavior and Human Resource Management
- Management Science and Operations Research