TY - CHAP
T1 - Preliminary Productivity Analysis of Conventional, Precast and 3D Printing Production Techniques for Concrete Columns with Simple Geometry
AU - Pekuss, Raitis
AU - García de Soto, Borja
N1 - Funding Information:
This research was funded by the 2019–2020 Post-graduation Research Fellowship Program at New York University Abu Dhabi (NYUAD). The authors would like to express their gratitude to Ana Anton and Dr. Timothy Wangler from ETH Zurich for their comments on the manuscript of this study and sharing information about the Concrete Choreography project. Further, the authors also wish to acknowledge Prof. Benjamin Dillenburger for developing the idea for Concrete Choreography.
Publisher Copyright:
© 2020, RILEM.
PY - 2020
Y1 - 2020
N2 - Significant advancement has been made in the field of additive manufacturing as applied to the construction industry. However, little attention has been paid to the implications of additive manufacturing, in particular 3D concrete printing (3Dcp), on the productivity of construction projects. The purpose of this study is to conduct a preliminary analysis of the productivity, measured in terms of cost and time per amount of material, for the construction of simple geometry concrete columns using conventional, precast, and 3Dcp techniques. The complexity of the geometry that can be achieved using 3Dcp was not factored in the comparison. Discrete-event simulations with data from the Concrete Choreography project were run. These results were compared with the productivity level achieved in the construction of a reinforced concrete column using conventional and precast construction methods. As expected, it was found that for the construction of simple geometry columns, 3Dcp is still not as productive as the other methods. These results should not be misunderstood as a lack of competitiveness of 3Dcp versus traditional methods. On the contrary, these results highlight the many benefits and capabilities of 3Dcp, which surpass the cost and time components. Some of them include topological optimization, geometric freedom, as well as increased transparency during the planning, design, and construction processes, which bring tremendous value to the 3Dcp elements. Quantifying these benefits is not trivial and is beyond the scope of this study; however, ongoing research is being conducted to address that.
AB - Significant advancement has been made in the field of additive manufacturing as applied to the construction industry. However, little attention has been paid to the implications of additive manufacturing, in particular 3D concrete printing (3Dcp), on the productivity of construction projects. The purpose of this study is to conduct a preliminary analysis of the productivity, measured in terms of cost and time per amount of material, for the construction of simple geometry concrete columns using conventional, precast, and 3Dcp techniques. The complexity of the geometry that can be achieved using 3Dcp was not factored in the comparison. Discrete-event simulations with data from the Concrete Choreography project were run. These results were compared with the productivity level achieved in the construction of a reinforced concrete column using conventional and precast construction methods. As expected, it was found that for the construction of simple geometry columns, 3Dcp is still not as productive as the other methods. These results should not be misunderstood as a lack of competitiveness of 3Dcp versus traditional methods. On the contrary, these results highlight the many benefits and capabilities of 3Dcp, which surpass the cost and time components. Some of them include topological optimization, geometric freedom, as well as increased transparency during the planning, design, and construction processes, which bring tremendous value to the 3Dcp elements. Quantifying these benefits is not trivial and is beyond the scope of this study; however, ongoing research is being conducted to address that.
KW - Additive manufacturing
KW - Construction automation
KW - Digital fabrication
KW - Labor productivity
KW - Time and cost analysis
UR - http://www.scopus.com/inward/record.url?scp=85088244967&partnerID=8YFLogxK
UR - http://www.scopus.com/inward/citedby.url?scp=85088244967&partnerID=8YFLogxK
U2 - 10.1007/978-3-030-49916-7_100
DO - 10.1007/978-3-030-49916-7_100
M3 - Chapter
AN - SCOPUS:85088244967
T3 - RILEM Bookseries
SP - 1031
EP - 1050
BT - RILEM Bookseries
PB - Springer
ER -