Abstract
Large-scale integration of wind farms causes volatile bus net injections. Although these fluctuations are anticipated, their timing, magnitude and duration cannot be predicted accurately. In order to maintain the operational reliability of the system, this uncertainty must be adequately addressed at the day-ahead generation scheduling stage. The ad-hoc reserve rules incorporated in deterministic unit commitment formulations do not adequately account for this uncertainty. Scenario-based stochastic unit commitment formulations model this uncertainty more precisely, but require computationally demanding simulations. Interval and robust optimization techniques require less computing resources, but produce overly conservative and thus expensive generation schedules. This paper proposes a transmission-constrained unit commitment formulation that improves the performance of the interval unit commitment. The uncertainty is modeled using upper and lower bounds, as in the interval formulation, but inter-hour ramp requirements are based on net load scenarios. This improved interval formulation has been tested using the IEEE RTS-96 and compared with existing stochastic, interval and robust unit commitment techniques in terms of solution robustness and cost. These results show that the proposed method outperforms the existing interval technique both in terms of cost and computing time.
Original language | English (US) |
---|---|
Article number | 7115977 |
Pages (from-to) | 970-982 |
Number of pages | 13 |
Journal | IEEE Transactions on Power Systems |
Volume | 31 |
Issue number | 2 |
DOIs | |
State | Published - Mar 2016 |
Keywords
- Interval optimization
- stochastic optimization
- uncertainty
- unit commitment
ASJC Scopus subject areas
- Energy Engineering and Power Technology
- Electrical and Electronic Engineering